Malaysia’s data centre (DC) boom is not letting up, but the rules meant to gauge its environmental toll are struggling to catch up. The source article does not name a Bursa-listed company or stock code, so this is a sector-level read for shareholders.
Why Malaysia’s Data Centres Need EIAs Before Building

The Environmental Impact Assessment (EIA) is the main tool for judging what a big project does to its surroundings. Yet it does not apply to data centres as a class.
Are Data Centres Covered by the 2015 EIA Order?
- Under the Environmental Quality Act 1974, an EIA is compulsory only for activities listed in a prescribed order.
- Data centres are not listed under the 2015 order now in force.
- A data centre can still be caught if another part of the project falls within a prescribed category.
In other words, whether a data centre gets scrutiny depends on how the project is packaged. Critics ask whether a facility that leans heavily on the grid and public water should be treated this lightly.
How Much Power and Water Will Data Centres Draw?
The government wants new DCs to generate their own electricity to ease grid pressure. That could mean gas-fired power plants sitting next to the facilities.
- The government is considering requiring DCs near ponds or other water sources to build their own water supply systems.
- Whether such a plant or water system needs an EIA depends on its size and classification, not on the fact that it serves a data centre.
- Small modular reactors (SMR) have been discussed for DCs, but nothing has been decided.
One environmental group estimates that 51 mapped DCs could emit nearly 44 million tonnes of CO2e a year. That is about a fifth of Malaysia’s 2024 emissions, and it is an advocacy group’s estimate.
Which Data Centre Projects Have Residents Already Objected To?
Fifty residents protested a proposed DC in Gelang Patah, Johor, in February 2026. Residents in three Kota Damansara neighbourhoods objected in July 2026.
They cited traffic, road safety, environmental impact and proximity to homes. These are the questions an EIA is meant to answer before construction, not after.
What Conditions Has the Government Set for Data Centres?
- The government says strict environmental conditions have been imposed and the companies have accepted them.
- DCs must source at least 30% of their power from renewables.
- Guidance reviewed by Sahabat Alam Malaysia calls for a 50m buffer between a DC and residential lots.
Conditions agreed with operators are not the same as law. An EIA gives the public a published study, a window to object, and a regulator who must justify its decision.
Could Malaysia Follow the US or China on Data Centre Rules?
The United States has had an EIA-style law since 1970, the National Environmental Policy Act. The administration has proposed categorical exclusions that would let AI-related DCs bypass lengthy environmental studies.
China relies on operating standards. New large and hyperscale DCs must meet set power usage effectiveness (PUE) levels, and those in national hub nodes must use over 80% green electricity. Beijing and Shanghai have reportedly capped water use at specific facilities.
Johor reportedly rejected nearly 30% of DC applications to conserve water and electricity. Critics warn that tighter rules could push investors to rival countries, but existing rules already work, they argue.
What Changes Should Bursa Investors Track in the Data Centre EIA Debate?
- The DoE should list DCs under the EIA Order, with thresholds based on power load, water use and proximity to homes.
- Assessments should weigh cumulative effects on grid and water supply in a district.
- Findings should be published, with a proper public comment period.
The Energy Commission is developing a framework and guidelines on self-generation facilities. Environmental review should be written into them from the start.
An EIA cannot be applied retroactively to a project already built, and approvals are running ahead of the rules. Listed companies with data centre or on-site power plans are worth monitoring against these rules. If you track filings, AI Stock Analysis for Malaysians can help you compare announcements.
Key Takeaways
- Data centres are not a prescribed activity under the 2015 EIA order now in force.
- Self-generated power and on-site water systems may escape EIA depending on their size and classification.
- Residents in Gelang Patah, Johor (February 2026) and Kota Damansara (July 2026) have already objected.
- Johor reportedly rejected nearly 30% of DC applications.
Frequently Asked Questions
Do data centres need an EIA in Malaysia?
Not in general. Under the Environmental Quality Act 1974, an EIA is compulsory only for prescribed activities, and data centres are not listed under the 2015 order now in force. A data centre can still be caught if another part of the project falls within a prescribed category.
How much CO2 could Malaysian data centres emit?
An environmental group estimates that 51 mapped DCs could emit nearly 44 million tonnes of CO2e a year. That is about a fifth of Malaysia’s 2024 emissions, and it is an advocacy group’s estimate rather than an official figure.
Does Johor reject data centre applications?
Johor reportedly rejected nearly 30% of DC applications to conserve water and electricity. The source does not give a breakdown by project.
What renewable energy share must data centres meet in Malaysia?
DCs are required to source at least 30% of their power from renewables. The government says strict environmental conditions have also been imposed on companies, which they have accepted.
Disclaimer: This article is for general information only and is not financial advice. It does not recommend buying, selling or holding any stock. Always do your own research before making investment decisions.
Source: View Original Article — The content is based on the original publisher. Refer to the original content for accurate info. Contact us for any changes.
Related Articles & Resources
Disclaimer: This article is for informational purposes only and does not constitute financial advice. Always do your own research before making investment decisions.
Want to invest in Bursa Malaysia or US markets? Contact Dexter Chia, an AI Driven Remisier who has 2,300+ clients at Malacca Securities Sdn Bhd (M+ Global). M+ Global Invitation Code: UBZQ | WhatsApp: +60169059789 | Why Choose Dexter?